The Navy has been able to reduce the expected cost of its Ohio Class submarine replacement by more than $1 billion with an overall goal of trimming more than $2 billion per vessel, according to the Pentagon's top weapons buyer.
Pentagon officials have generated the extra cost savings by examining the drivers of cost in the vessel's design, according to Pentagon acquisition executive Ashton Carter.
Originally, cost estimators projected the SSBN(X) price tag at about $7 billion per submarine. The submarine's cost is now down to $6 billion with a goal of getting the cost down to $4.9, Carter said during a Feb. 22 presentation at a Center for New American Security event in Washington.
If the Navy were forced to pay $7 billion per submarine, it would not be able to afford any other ships, Carter said.
This same approach of looking at the drivers of cost in a weapon's design will be used during upcoming acquisitions, including the Air Force's new bomber, a Marine Corps effort to field a new helicopter for presidential transport and the Army's Ground Combat Vehicle, Carter said.
Pentagon officials have generated the extra cost savings by examining the drivers of cost in the vessel's design, according to Pentagon acquisition executive Ashton Carter.
Originally, cost estimators projected the SSBN(X) price tag at about $7 billion per submarine. The submarine's cost is now down to $6 billion with a goal of getting the cost down to $4.9, Carter said during a Feb. 22 presentation at a Center for New American Security event in Washington.
If the Navy were forced to pay $7 billion per submarine, it would not be able to afford any other ships, Carter said.
This same approach of looking at the drivers of cost in a weapon's design will be used during upcoming acquisitions, including the Air Force's new bomber, a Marine Corps effort to field a new helicopter for presidential transport and the Army's Ground Combat Vehicle, Carter said.