Thursday, March 17, 2011

Scorpene Delivery to India Delayed 3 Years

NEW DELHI - Delivery of the first French Scorpene submarine being license-built in India has been delayed by three years, until the latter part of 2015, Indian Defence Minister A.K. Antony told the Indian Parliament in a written statement March 14.
According to the $3.9 billion contract signed in 2005 between India and France, construction of the first three submarines would begin in December 2006, December 2007 and August 2008. As per the contract signed with Mazagon Docks Ltd. (MDL), the first submarine is scheduled to be delivered in December 2012, and one each year until December 2017, Antony said.
Antony, however, told Parliament that the first Scorpene delivery will be delivered in 2015.
"As per the contract, the first submarine was scheduled to be delivered in December 2012 and thereafter, one each every year till December 2017. There have been delays due to initial teething problems, absorption of complex technology, augmentation of MDL infrastructure and procurement" of material. The first submarine is now scheduled to be delivered in the second half of 2015, Antony said.
India is already facing a shortfall in submarines. Currently, the Navy has 14 submarines and, by 2012, there will be nine, a senior Navy official said.
The news of the delay in the Scorpene delivery comes at a time when the Chinese Navy is building several nuclear submarines. China has about 30 modern submarines and few dozen older ones. The Scorpenes are being built under Indian Navy's Project 75, which was approved in 1997.
The Scorpene is a conventional submarine with diesel propulsion. It is 219 feet long and has a speed of more than 20 knots with a displacement of 1,700 tons. With 31 men onboard, it can remain at sea for about 50 days and can dive to a depth of more than 1,000 feet.

No comments:

Post a Comment